NCRMP
  Page 1 of 4
 

 

 

Basic Information on
National Cyclone Risk Mitigation Project (NCRMP)
As on 31.03.2013
1.     Overview:
1.1          National Cyclone Risk Mitigation Project (NCRMP) has been drawn up to strengthen the structural and non-structural mitigation efforts towards reducing the risk and vulnerability of the coastal districts to cyclone-related disasters. Implementation of NCRMP in Odisha has been approved in Phase-I of a Centrally Sponsored Scheme. The central share is being funded by the World Bank as an Adaptable Programme Loan with an International Development Association (IDA) credit.
1.2          The Financing Agreement between the World Bank and the Government of India and the Project Agreement between the World Bank and the State Government were signed on January 14, 2011. The Project Agreement became effective on March 30, 2011 and the project was formally launched on April 25, 2011. 
1.3      The project for Odisha is being implemented in six coastal districts such as Balasore, Bhadrak, Ganjam, Jagatsinghpur, Kendrapada and Puri during the period 2010-11 to 2014-15. The closing date of the project is October 31, 2015.
1.4        The project has a total financial outlay of Rs.653.79 crore with earmarked fund for component A, B, C, D and an unallocated amount of Rs.58.20 crore. Components A, C and D are fully funded by the Central Government. However, component B (Rs.518.95 crore) is being funded by the Central and the State Governments on the ratio of 75:25. The Component wise approved financial outlay under NCRMP for Odisha is as below:
                                                                                                                                  (Rs. in crore)

Sl.
No.
Components
Sector
Allocation for Odisha
1
Component-A
Early Warning Dissemination System
38.80
2
Component-B
Cyclone Risk Mitigation Infrastructure
Construction of multipurpose Cyclone Shelters & godowns
145.50
Shelter connectivity
218.25
Raising and strengthening of Saline Embankment
155.20
Sub_Total
518.95
3
Component-C
Technical Assistance for Capacity Building on Disaster Risk Management
2.43
4
Component-D
Implementation Assistance
35.41
Unallocated and Contingency @10% of overall cost
58.20
 Grand Total
653.79
       

2. Pre-implementation Processes: Before implementation of the project,a number of processes were followed as per World Bank guidelines. The major processes are as below:
2.1 Sub-components: The project has following three sub-components:
·         Construction of multipurpose cyclone shelters and godowns: 156 (150 MCS + 6 Go-downs)- 151 packages
·         Approach roads: 73 packages comprising of 248.325 km length of road

Raising and strengthening of saline embankments: 10 prioritized embankments in 12 packages comprising of 61.062 km.

      2.2 Project Phasing:

Components
Total
Year – I
Year-II
Construction of multipurpose Cyclone Shelters
(150 Cyclone Shelters + 6 Go-downs)
80 Cyclone Shelters in 75 packages
69 Cyclone Shelters + 6 Go-downs in 75 packages
Shelter connectivity
73 packages of approach roads 176.97 km
29 packages of approach roads 64.01 km
44 Packages of approach roads 112.96 km
Raising and strengthening of Saline embankt
61.062 km
61.062 km in 10 embankments in 12 packages
                                                              