2. What are the projects (including amounts involved) executed through OSDMA under World Bank funding and the amount involved?

1.   Raising/ strengthening/ renovation/ construction of embankment, spurs, sluices, etc.: (Rs.109.61crore)

  1. Flood embankment - 877 km
  2. Canal embankment  - 332 km
  3. Spur     - 82 Nos.
  4. Sluices - 19 Nos.

2.   Roads repaired / renovated: (Rs.105.71crore)

  1. Works Department - 275 km
  2. R D Department - 448 km
  3. Urban road under H & UD Dept. - 85 km 

3.   Water Supply: (Rs.9.19crore)

  1. Installation of pump sets, construction of bore wells, tube wells and laying of pipe lines in
  2. Urban locations - 20
  3. Rural locations - 64

4.   Cyclone Shelter constructed- 37 (Rs.18.32 cr.)
5.   Agro Service Centres set up- 500 (Rs.10crore - subsidy)

  1. Total expenditure including expenditure on project management - Rs.269.95crore
  2. Amount reimbursed by WB- Rs.222.12cr. 

Portion of a few works which could not be completed under with World Bank project in the stipulated project closure period have been completed with CRF assistance.


 

State Coordinates

20.15° N 85.50° E

Date and Time

20-Aug-2019 08:28:05

Current Weather

Control Room

State EOC(BBSR) Toll Free Number - 1070

Other Phone Numbers -0674- 2395398, 2395531

Fax - 0674-2391871

Copyright @ 2017 . All Rights Reserved